« Back to News & Notices

Enbridge Update

8/27/2025

Portage Update August 2025 

The Portage Expansion construction work is nearing its end. See below progress bullets for  August 2025:  

IHP distribution gas mains are 100% installed (final footage at 34,778). 

The 6” high pressure gas main is around 90% complete, with final tie-in scheduled for  9/29/25. 

The natural gas system, including the pressure regulator station, is expected to be in service  by Oct 15, 2025. 

If there have any concerns about the construction work, please call our contractor, Whitaker  Construction: 

o Kevin Gibbons (801-589-0569) 

o Jeremy Cox (801-520-4227) 

Service line sign-up notes 

Please contact Bradon Swapp (801-391-1369) to sign up for a natural gas service line.  Residents can also sign up for service through our rural expansion page (Utah Rural  Expansion Program | Projects | Enbridge Gas

As a reminder, customers will have two years from the time the natural gas system is  complete (expected 10/1/25) to sign up for their service line. 

Gas service can commence after the natural gas system is complete, the service line is  installed to a residence, and home fuel lines are inspected and approved by a county official.  In addition, an account and meter set must be set up prior to providing gas service.  Accounts and scheduling meter sets can be initiated by calling contacting Enbridge Gas  (801-324-2100).

Dominion Energy is now Enbridge Gas in Utah, Wyoming and Idaho. Read more about the  transition on dominionenergy.com. 

Revised 08/25